PATHFINDER ARRIVES AT LAUNCH SITE
A look into the flight readiness campaigns behind Pathfinder’s early 2027 launch and what it means for Nova Block 2.
Stage 1 on the road to Cape Canaveral, Florida
From the rocket factory to the launch pad
On November 22nd, our Cape Canaveral team received Nova Pathfinder’s first stage at Space Launch Complex 14 (SLC-14). It is the first Nova stage to arrive at the pad, and the first rocket at SLC-14 in 60 years.
Nova is built to be transported on public highways. This enables the rocket to be built in a single location while being launched from anywhere, limiting capital outlay and removing the need to transit the Panama Canal. However, it sets dimensional constraints and drives certain structural requirements for the rocket since it must withstand road loads, as well as flight loads. The journey from one corner of the country to another took 17 days, 10 hours, 52 minutes and by all accounts appears to have gone smoothly.
Throughout the year we’ve shared Pathfinder’s progress in short updates, but today, we’re going deeper. Stoke is organized around rigorous and rapid testing across every subsystem that comprises Nova. The speed of that testing, and the iterations that go with it, is what defines the pace of the program.
We spent 2026 finding the performance ceilings of Pathfinder long before it arrived at the pad. Most of what we learned lives in test data, and all of it advanced readiness for first flight that’s already shaping Block 2.
Below is a look into that work and what comes next.
Stage 1 preparing for structural testing in Moses Lake, WA
Structural qualification
The Stage 1 that just arrived at the Cape is the same structure we put through structural and fluids testing at our Moses Lake Test Site (MLTS) in May.
A rocket has to be light enough to fly and strong enough to survive shipping and handling, cryogenic propellant, pressure cycles, and the dynamic structural and thermal loads of launch and reentry. The margin between these requirements and the design limits is narrow by necessity. Structural qualification is where new vehicles often find problems.
Our qualification program started with material test coupons, which we use to quantify material strength before and after each of our manufacturing processes. Heated and cryogenic "dogbone" tests prove the integrity of our welds and other processes at representative temperatures. Those collections of data feed directly into the design, and they’re used to structure the test matrix that defines the qualification test campaign.
That qualification campaign involved two different "Tiny Tank" ground test articles, as well as additional testing on the flight vehicle itself. The “Tiny Tanks,” which were full-scale diameter but shorter lengths, were used to stress the structure beyond the designed margin, including taking Tiny Tank 1 to burst in 2025. In 2026, Tiny Tank 2 qualified the Stage 1 aft barrels for use with broader operational limits than previous testing would have allowed.
Qualification testing on flight hardware is known as proto-qualification, or protoqual. Over three weeks in May, the Stage 1 flight article underwent a protoqual campaign that involved 46 structural test objectives and loaded the stage to 115% of expected flight loads. Hundreds of strain gauges confirmed the structure behaved the way our models predicted. Post-test inspection found no damage and no detrimental yielding anywhere on the vehicle. The campaign also exercised the fluid systems, avionics, software, ground systems, procedures and operations team that fly with the stage.
In addition, we tested less obvious load-defining cases, such as the cantilevered load Stage 2 places on Stage 1 when the two are mated horizontally. To do so, we mounted a Stage 2 mass simulator on the Stage 1 separation interface and loaded it in shear, with load cells at every attachment point. That test qualified the vehicle lift interfaces and the stage-to-stage load path in flight geometry.
Stage 1 shipped to SLC-14 shortly thereafter.
Launch livestream software graphical user interface (GUI)
Avionics & flight software
Stoke develops its own avionics components, systems, and flight software stack. In addition to its use on component and subsystem test stands, the proving ground for these elements is Flatrocket, our hardware-in-the-loop (HITL) bench; every flight computer, stage controller, engine controller, servo driver, navigation unit, radio, and payload controller that flies on Pathfinder is connected with flight-representative harnesses and linked to Guidance, Navigation, and Control (GNC) logic that simulates the physics of the tanks, propellants, engines and trajectory.
Through 2026 we ran thousands of flight and ground operations simulations with Flatrocket. By summer we were running end-to-end operations, from dry tanks through propellant load, static fire and de-tanking, using the same sequences and controllers that run our test and launch sites.
That bench is also where we simulate and practice our response to anomalies; we might cut power to a stage controller mid-count and watch the vehicle respond or fail a navigation sensor to exercise a pre-launch abort. None of these are experiments you want to run for the first time on a fueled rocket.
The lab and the vehicle share the same stack. Stoke's vehicle software runs across a system of 100+ deployments across test stands, HITL benches, manufacturing cells and development rigs, all managed from a common stack with recurring automated rollouts.
Before leaving the factory in Kent, full mission simulations were performed on both stages. This involved powering up the rocket, running a real terminal count and flight simulation with tank pressure control, stage separation mechanisms, and other flight systems in the loop. Stage 2 was tested in this way in September, followed by Stage 1 in October.
Successful fairing jettison test
Separation systems
Every single component has its own qualification campaign before it ever makes it onto the rocket. The S1-S2 stage separation mechanisms completed qualification across static proof, vibration, hot, cold, and ambient performance, life cycling, and ultimate loads driven by Pathfinder’s full payload capability.
Similarly, a successful full-scale fairing jettison demonstration was completed using flight fairing and payload attachment hardware. These are one-shot systems, so we qualify them by testing identical units from the same production lot as the flight hardware.
Stage 2 flight article arrives at our site in Moses Lake, WA for acceptance test protoqual
Stage 2 cryogenic proof
Stage 2 shipped to Moses Lake in late October and went vertical on its test stand within 24 hours of arrival to the site. In early November, we completed its structural proof testing with cryogenic propellants loaded; the oxidizer tank, the common dome, and the fuel tank were each taken to 110% of maximum design pressure and held for five minutes. There were no structures anomalies. This acceptance testing followed a more rigorous structural qualification program that was conducted on a full-scale equivalent structure in 2025.
Following the structural acceptance tests, which were done with inert cryogens, a full Wet Dress Rehearsal was performed with the stage’s liquid hydrogen and oxygen propellants. This test rehearsed the full pre-launch sequence, filling the tanks to their full flight load. The vehicle performed nominally on the first attempt.
The next (and last) step for Stage 2 is a static hotfire test, which will be conducted at MLTS after installing the Andromeda engine onto the vehicle.
Comparison of Andromeda and Zenith engine hot fire tests
Zenith and Andromeda
Both engines moved through development and into flight acceptance testing within the same fifteen-month period. As of this writing, acceptance tests have been completed on the Flight 1 Andromeda as well as four out of the seven Zenith engines, with the remaining engines actively moving through the process.
Within that fifteen-month period we hot fired 64 different engine hardware configurations across 219 engine starts, for more than six hours (21,845 seconds) of hot fire, running as many as 28 starts in a month, nine in a week and five in a single day. The team in Moses Lake ran a further 1,271 component tests in the same period, including turbopump spins and powerpack hot fires, igniter qualification firings, preburner and injector tests, valve cycling and thruster-pod hot fires.
This is what it takes to develop two of the most sophisticated engines in the industry.
During development, Zenith went through four distinct block configurations over a two-year period before the design was locked for flight qualification and acceptance testing. These changes encompassed performance and producibility improvements to the turbopumps, valves, thrust chamber, nozzle, cooling circuit, TVC actuators, and other components. It even included bringing seal production brought in house; the first in-house designed seal was installed on an engine within three weeks from making the decision.
Once these development iterations were complete, we performed nearly 10,000 seconds of test time over five months to finalize and qualify the engine for flight. Our two qualification engines alone drew 7,647 seconds across 91 starts, about ten times the 760-second initial service life requirement.
Zenith engine life for development and qualification engines
Andromeda engine life for development and qualification engines
When Nova’s second stage reenters the atmosphere, it’s protected by an actively cooled metallic heat shield that is integral to our Andromeda hydrogen-oxygen engine. Active liquid cooling enables the heat shield to have a ductile metallic construction that can endure a long service life without refurbishment. Ultimately, the level to which inspection and refurbishment is required between flights will determine the recurring flight cost and cadence. This is the thesis the company was founded on, and it’s the first thing we started working on.
Andromeda is also the most novel facet of Nova's architecture. The first development engine, carrying thirty thrusters, fired in February 2024. Roughly 50 distinct hardware configurations and 242 engine starts later, the engine can be manufactured, integrated and tested repeatably. Most of those stats were earned in the last fifteen months, across three engines, 30 hardware configurations, 72 starts, and 10,825 hot-fire seconds. The qualification campaign included 28 starts and 5,177 seconds, reaching twice its rated flight life.
Almost all of that testing was performed with a single heat shield, which withstood both nominal and extremely off-nominal conditions. Through the course of this, we also demonstrated that if the engine’s heat shield needs repair at some point in its service, we can do it; a crack found in the heat shield was repaired and returned to service for a full-duration mission duty cycle (MDC) test burn within eight days.
Both programs require an investment in the ability to design, manufacture, assemble and test high-complexity machines in one place. That capability feeds straight into what comes next, with Block 2 development testing slated to begin at Moses Lake next year.
Pathfinder’s first stage flies seven Zenith engines, and Block 2 flies 14. Just as it has before, Zenith will continue evolving ahead of Nova’s Block 2 debut — thrust, performance, and producibility all improve with reps — but the cycle does not change and neither does the underlying architecture. It is the same full-flow staged combustion engine, burning the same propellants, built on the same production system. Every second of hot fire we put on Zenith advances the Block 2 engine as well.
SLC-14 in Cape Canaveral, Florida
Test & launch infrastructure
Investing in our own test and launch infrastructure is one of the keys that enables us to test and iterate quickly. As a small example, at one point we learned about a tolerance problem in a turbopump joint on a Thursday morning, measured it across several pumps that afternoon, cut and tested a first revised pin by Friday lunchtime, and had over a dozen parts in hand by the end of that day. A ten-day insulation plan on Stage 2 was hit to the day, and Stage 1 structural qualification pulled five days out of the program schedule.
In 2026 we brought online a cryogenic seal test rig, a development test cell for Stage 2 igniters, a second thrust-vector-control friction stand, a larger vibration table, a component test cell at SLC-14 in Cape Canaveral, a pneumatic proof enclosure that lets us proof flight hardware during working hours instead of clearing the factory, and other critical capabilities.
Stoke builds its own test stands, data acquisition, avionics and flight software, and the people who designed each system are the ones reviewing the data.
Boltline, the AI-powered hardware execution platform we built to develop Nova and run our operations, tracks the configuration of every part and build, so each data point traces back to the exact hardware and software that produced it. Owning every link in that chain means we can find the cause of a problem, fix it and be back on the stand within days.
And the footprint is growing. Earlier this month, Space Launch Delta 45 granted Stoke Right of Entry (RoE) to expand into the property north of SLC-14. That authorizes engineering studies, environmental assessments and site surveys for an expansion that includes a second launch pad, built for high cadence launch and landing operations for Nova.
Nova Block 2 rendering
Pathfinder readiness is Block 2 readiness
Everything we’re building for Pathfinder is designed for forward-traceability to Nova Block 2. Pathfinder’s Zenith FFSC booster engine, hydrogen-powered Andromeda engine, and actively-cooled metallic heat shield are all high-visibility elements that carry forward to Block 2. But the less visible items are perhaps even more important.
The stainless-steel skin-and-string design, along with our in-house developed construction and verification methods, make our primary structures scalable to arbitrary size without expensive fixed tooling. The weld schedules, proof factors, environmental correction factors and test stands that qualified Pathfinder are the same ones Block 2 inherits. Similarly, the valves, actuators, seals, avionics, harnesses, software, and other components all carry forward. Most importantly, the team, the know-how, and the infrastructure create an accelerating flywheel.
We haven’t even launched Pathfinder yet, but both its first launch and Block 2 will be here before we know it. And when it arrives, it won’t just address the increasing void in the medium-lift launch market, but it will also be able to carry payloads back from orbit. This gives researchers and manufacturers the ability to recover experiments and products made in microgravity, and defense programs the new opportunity to inspect hardware after it flies. The same ability to reenter and land underpins our work with the Defense Innovation Unit (DIU) on point-to-point cargo delivery. Those are new markets for American industry, and each of them starts with the tests in this post.
Reverence for the challenge
Stage 2 will perform a static fire test at MLTS in December before shipping to Cape Canaveral. Stage 1 is in the Horizontal Integration Facility (HIF) at SLC-14 in preparation for a series of wet dress rehearsals that have the new launch pad in the loop. The remaining Zenith engines will then be integrated with the stage, culminating in a stage static fire. Following these final verifications, Stage 2 will join Stage 1 in the HIF. And then, we launch.
Pathfinder is the vehicle that will demonstrate our fully reusable architecture. We view each test as a task order to get Nova Block 2, a 15 metric ton fully and rapidly reusable rocket, flying in 2029.
To our customers, partners, and investors: thank you for building with us. While we’re proud of our progress, there is a very long (and exciting!) road ahead. We’ll continue grinding through the details, verifying through test, and improving through iteration.
Done right, that translates to full speed ahead. And if that sounds exciting to you, we’re hiring.